Warehouse Storage Installation at an East Texas Power Plant


Challenge:

  • Client needed effective space for maintenance operations as well as shipping and receiving operations.

Solution:

  • Create a custom storage and shelving system that would work for the client while not effecting client’s ongoing operations.

Concept:

  • Russell Industries installed a mezzanine with an inplant (air conditioned) office under the mezzanine. The mezzanine was made of structural steel with bar grating to support the floor. The other components to this project include all steel sectional shelving under the mezzanine and selective pallet racking. Russell Industries also installed drawers that were embedded in each section of the shelving at the bottom for adequate storage space for the client’s day to day activities. The project was also completed under budget.

Time:

  • 1 week (including fabrication and installation)

 